# BIM execution plan (pGI): what it contains and when it is written

The BIM execution plan (pGI) turns the tender plan into operating rules: who writes it, when it is submitted, what it contains and how it is updated.

**Topic**

Guides

**Published**

20 November 2026

**Author**

B1P Group editorial team

[Have a question? Write to us](https://www.b1pgroup.com/en/contact/#scrivi)

The **BIM execution plan** (piano di gestione informativa, pGI) is the document in which the successful tenderer sets out how it will manage the project's information: who does what, with which models, on what timescale and with which checks. It responds to the [exchange information requirements](https://www.b1pgroup.com/en/bim-news/exchange-information-requirements-what-they-are-and-who-writes-them/) and, when a [pre-appointment BIM execution plan](https://www.b1pgroup.com/en/bim-news/pre-appointment-bim-execution-plan-bep-contents-and-assessment/) was submitted in the tender, develops it. In UNI EN ISO 19650 terms it is the post-appointment BEP.

## Who writes it and when

The successful tenderer writes it, based on the pre-appointment BIM execution plan submitted in the tender; if the tender was awarded on lowest price and there is no such plan, the reference remains the exchange information requirements. What happens when the pre-appointment BEP is missing in a tender that requires it is explained in the article [Can I be excluded from a tender if the pre-appointment BEP is missing or incomplete?](https://www.b1pgroup.com/en/bim-news/missing-or-incomplete-pre-appointment-bep-tender-exclusion/). In public procurement of design services and works, Annex I.9 to Legislative Decree 36/2023 (paragraph 10) requires it to be submitted to the contracting authority after the contract is signed and before execution, and allows it to be updated during the contract. If execution starts urgently, the contracting authority can ask for it before signature. In private contracts the contract sets timing and procedures.

## What the BIM execution plan contains

- **Roles and appointments**: the information management roles, from the manager of digital processes (BIM manager) to the manager of the common data environment (CDE manager), with responsibilities and contacts.
- **Model structure**: breakdown by discipline and part of the asset, federated model, coordinate system and units of measurement.
- **Naming and classification rules** for files, models and objects.
- **Levels of development or of information need** for each phase and each delivery.
- **Delivery schedule**, with contents and formats, native and IFC.
- **Coordination and checking**: the levels of coordination and checking of UNI 11337-5, tools, frequency, issue management.
- **Common data environment rules**: information states, permissions, approval workflows. In public works deliveries go through the contracting authority's CDE.
- **Changes and model updates** during the works, up to the as-built model.

## From the pre-appointment plan to the BIM execution plan: what changes

When a pre-appointment BIM execution plan was submitted in the tender, moving to the BIM execution plan changes the nature of the document: the pre-appointment plan is written for the evaluation panel, the BIM execution plan is an operating commitment. In the transition, descriptions become names, dates and procedures: the roles listed become people, timescales become a schedule, checks become reviews with someone responsible. What the pre-appointment plan promised remains a commitment: if the real organisation cannot sustain it, it is better to find out here than on site.

|  | Pre-appointment BIM execution plan (oGI) | BIM execution plan (pGI) |
| --- | --- | --- |
| Who writes it | The bidder | The successful bidder |
| When | During the tender, with the bid | After the contract is signed and before work starts |
| Nature | A proposal assessed by the evaluation panel | An operational commitment to the contracting authority |
| Content | How the bidder intends to meet the exchange information requirements | Names, dates, procedures and responsibilities |
| Updating | Cannot be changed after the deadline | Updated during the contract |

## How it is updated

The plan is not signed and then filed away. It is updated when roles, phases, subcontractors or deliveries change, with a revision tracked in the common data environment. It must also say who updates the model with the changes made on site, because at the end of the works Annex I.9 requires the contractor to hand over the models updated as built, with a report on their compliance with the exchange information requirements.

## Frequently asked questions about the BIM execution plan

### Who writes the BIM execution plan?

The successful tenderer, starting from the pre-appointment BIM execution plan submitted in the tender or, if none was required, from the exchange information requirements.

### When is the pGI submitted?

In public procurement after the contract is signed and before execution, by submitting it to the contracting authority (Annex I.9, paragraph 10). If execution starts urgently, the contracting authority can ask for it before signature.

### Can the pGI be changed?

Yes: Annex I.9 allows it to be updated during the performance of the contract. Each update must be tracked and shared.

### What is the difference between the pGI and the BEP?

BEP (BIM execution plan) is the UNI EN ISO 19650 term and covers two stages: the BEP submitted before the appointment corresponds to the offerta di gestione informativa (oGI), the one after the appointment to the piano di gestione informativa (pGI).

### Is the pGI used in private contracts too?

Yes, if the contract provides for it: it is how client and suppliers put in writing the rules, timescales and responsibilities of information management.

## Sources

- Legislative Decree no. 36 of 31 March 2023, Annex I.9, art. 1, paragraph 10, as amended by Legislative Decree 209/2024
- UNI 11337-5 and UNI/TR 11337-6
- UNI EN ISO 19650-2

## How we work

For designers and contractors that have won the tender, B1P Group writes the BIM execution plan following the structure of the requirements, point by point, and keeps it up to date during the project with its [BIM management](https://www.b1pgroup.com/en/services/bim-management/): roles, common data environment, coordination and checking of the models before each delivery.

Further reading [BIM management and information management](https://www.b1pgroup.com/en/services/bim-management/)[BIM tender support](https://www.b1pgroup.com/en/services/bim-tender-support/)[BIM glossary](https://www.b1pgroup.com/en/bim-glossary/)