4D adds time to the model: each object or group of objects is linked to an activity in the programme, so construction is simulated as a visible sequence and planned progress is compared with actual progress. 5D adds cost: the object quantities feed the bill of quantities, procurement and works accounting, and physical progress becomes financial progress.
The value lies not in the animation but in consistency: the same quantity is used for the estimate, the purchase order and the interim valuation, and the same date is used by the site manager and by the works supervision team.