Exchange information requirements: what they are, who writes them and what they contain

The exchange information requirements state what the client wants from the BIM models: who writes them, what Annex I.9 asks for and the mistakes to avoid.

Topic
Guides
Published
20 November 2026
Author
B1P Group editorial team
Have a question? Write to us

The exchange information requirements (capitolato informativo, CI) are the document in which the client sets out what it wants to receive from the information management of a project: which models, with what information, in which formats, with which rules and checks. In public works they are one of the tender documents required by Annex I.9 to Legislative Decree 36/2023; in private contracts they are the simplest way to avoid BIM meaning something different to each party. In UNI EN ISO 19650 terms they are the EIR.

Who writes the exchange information requirements

The client. In public works the contracting authority prepares them and attaches them to the tender documents: for architecture and engineering services this is set by paragraph 8 of Annex I.9, for works by paragraph 9, which requires them to be consistent with the level of the design put out to tender. Tenderers do not write them: in tenders awarded on the most economically advantageous tender they respond with the pre-appointment BIM execution plan. The client can be supported by a consultant, but the document remains the client's.

What Annex I.9 asks for

For architecture and engineering services the exchange information requirements contain at least:

  • the strategic and specific information requirements, including the levels of information need;
  • the elements for defining how information is produced, managed, transmitted and archived;
  • the specifications of the common data environment, with data ownership and the conditions for access and security;
  • the specifications for long-term interoperability of the systems.

For works, the contract documents also define the contractor's responsibilities and obligations in digital information management.

How they are organised in practice

The technical report UNI/TR 11337-6, the guideline for the exchange information requirements set out in UNI 11337-5, divides them into a technical section and a management section. Whatever the structure, complete requirements always cover the same topics: hardware and software, exchange formats (native and IFC), coordinate system, classification and naming, common data environment, objectives and uses of the models, levels of development or of information need by phase, roles and responsibilities, model structure, coordination and checks, delivery timescales and contents, the as-built model.

The most common mistakes

  • Asking everyone for everything: high levels on every object, without linking them to a use. The result is generic bids and costly models that nobody uses.
  • Copying the requirements of another asset: type, phases and uses change, and the requirements no longer fit.
  • Not coordinating requirements and tender rules: if the award criteria do not refer to the requirements, the bids do not address them.
  • Leaving deliveries vague: without timescales, formats and acceptance checks, the as-built model becomes a negotiation at the end of the works.
  • Forgetting operation: if the asset will be managed with the model, the requirements must ask from the start for the information needed in operation.

Requirements, pre-appointment plan and BIM execution plan

The three documents follow one another: the client's exchange information requirements, the pre-appointment BIM execution plan submitted in the tender when it is required, and the BIM execution plan written by the successful tenderer. Every requirement should reappear, with its answer, in the pre-appointment plan and then in the BIM execution plan.

DocumentWho writes itWhenWhat it is for
Exchange information requirements (capitolato informativo, CI)Contracting authority or clientBefore the tender, among the tender documentsSets the information requirements
Pre-appointment BIM execution plan (oGI)BidderDuring the tender, with the bidStates how the requirements will be met
BIM execution plan (pGI)Successful bidderAfter the contract is signed and before work startsTurns the bid into operating rules

Frequently asked questions about exchange information requirements

Who writes the exchange information requirements?

The client; in public works the contracting authority, which attaches them to the tender documents. Tenderers do not write them: in tenders awarded on the most economically advantageous tender, they respond with the pre-appointment BIM execution plan.

Are exchange information requirements mandatory?

In public works where BIM is mandatory, or where the contracting authority chooses to adopt it, yes: Annex I.9 lists them among the tender documents. In private contracts there is no legal obligation, but without them the requirements stay undefined.

What is the difference between the capitolato informativo and the EIR?

They are the same thing: EIR (exchange information requirements) is the name UNI EN ISO 19650 gives to the information requirements of an exchange, which in Italy are collected in the capitolato informativo.

Do the requirements ask for LOD or LOIN?

They can ask for both. Many requirements use the levels of development of UNI 11337-4 (LOD, from A to G); Annex I.9 speaks of levels of information need, the LOIN of UNI EN ISO 7817-1, which links each piece of information to the purpose it serves.

Who checks that the models meet the requirements?

Those who produce the models check them before each delivery; acceptance checking stays with the client. At the end of the works Annex I.9 requires the contractor to hand over the models updated as built, with a report on their compliance with the requirements, which the testing and acceptance body checks.

Sources

  • Legislative Decree no. 36 of 31 March 2023, Annex I.9, art. 1, paragraphs 8, 9 and 10, as amended by Legislative Decree 209/2024
  • UNI 11337-4, UNI 11337-5 and UNI/TR 11337-6
  • UNI EN ISO 19650-1 and UNI EN ISO 19650-2
  • UNI EN ISO 7817-1

How we work

For clients, B1P Group writes the exchange information requirements following Annex I.9 and UNI/TR 11337-6, tailored to the asset and to the real uses of the models. For designers and contractors it reads the tender requirements and prepares the bid that answers every requirement, with its BIM tender support.